A user acceptance testing plan that ends in a clear decision: acceptance criteria for each requirement, scenarios business testers can run, severity rules that say what blocks, and a sign-off block with conditions.

By the TestPlum teamChecked

Short answer

A UAT test plan says which business processes the people who will use a change must accept, the acceptance criteria for each requirement, when UAT starts and ends, who tests and who decides, and which defects block sign-off. This template, as an Excel workbook or Markdown, adds a scenario table, a defect log and a sign-off block with name, role, decision, date and conditions.

What a UAT test plan is for

User acceptance testing (UAT) is the last check before a release: the people who will use a change, such as customer service, finance or operations, confirm it lets them do their job. QA testing asks whether the software works as specified. UAT asks whether what was specified is what the business needs, in the way the business works.

That makes UAT different from the rest of testing in three ways. The testers are not testers by trade, so scenarios must be written in their language. The output is a decision, not a pass rate: accepted, accepted with conditions, or rejected. And the decision belongs to a named business owner, who needs to see the evidence behind it.

Write the UAT plan once the requirements for the release are agreed, and agree it with the business owner before UAT starts. It sits next to the lean test plan, which covers system and regression testing; the UAT plan picks up where that one ends.

What is in the template

The Excel version puts each part on its own sheet (Plan, Requirements, Criteria, Roles, Scenarios, Defects, Summary and Sign-off) with dropdowns for results, severity and the decision. The Markdown version is one page for a wiki or a repository. Both are filled with the same example: a checkout release accepted by customer service, marketing and finance.

The sections of the UAT test plan and sign-off template
SectionWhat to write
ScopeThe business processes this release changes, and what is out of scope and why.
Requirements and acceptance criteriaEach requirement in scope with two to four criteria a business tester can check.
Entry criteriaWhat must be true before business testers start.
Exit criteriaWhat the business owner signs against.
People and rolesBusiness owner, UAT lead, business testers and who fixes defects.
Test dataThe accounts, codes and cards the scenarios need.
ScenariosWhat each tester does and expects, and the result.
Defects and severity rulesEach defect with its severity, and which severities block sign-off.
Sign-offName, role, decision, date and conditions.

Acceptance criteria for each requirement

Acceptance criteria turn a requirement into statements a business tester can check and get the same answer as anyone else. Two to four per requirement is usually enough. Each criterion is checked by at least one scenario, and the Scenarios column makes that link visible, so a requirement with no scenario stands out before UAT starts.

  • Write outcomes, not features. “The refund equals the amount charged, after the discount” can be checked. “Refunds work” cannot.
  • Include the business side. In the example, REQ-14 is not accepted until the finance export shows the discount, because that is where finance would notice a mistake.
  • Put numbers in. “Within 5 minutes” and “15% off full-price items only” settle arguments before they start.
  • Agree them before UAT starts. Criteria written after a scenario fails tend to describe what the software does instead of what the business needs.
Example requirements and acceptance criteria from the UAT template
RequirementAcceptance criteriaScenarios
REQ-12 Customers can pay with a saved cardThe saved card is preselected at checkout. The confirmation email arrives within 5 minutes and shows the last four digits of the card.UAT-1
REQ-13 A declined payment shows a clear error and keeps the cartThe customer sees “Your card was declined” and the cart is unchanged. Customer service can see the declined attempt on the customer's record.UAT-2
REQ-14 A valid discount code reduces the subtotalSPRING15 takes 15% off full-price items only. The daily finance export shows the discount on its own line.UAT-3, UAT-4
REQ-17 Customer service can refund a paid orderA full refund sets the order to Refunded. The refund equals the amount charged, after the discount.UAT-5

Entry and exit criteria for UAT

Entry criteria protect the business testers' time. If they start on a build QA has not finished with, they find bugs QA would have found, lose trust in the build and stop turning up. Exit criteria protect the decision: they are what the business owner signs against, so agree them before the first scenario runs and answer each with a yes or a no.

Entry and exit criteria in the UAT template
TypeCriterionWhy it is there
EntrySystem and regression testing are finished and their exit criteria are metBusiness testers should not be finding bugs QA would have found.
Entry0 open bugs of blocker or critical severity in scopeA known serious bug wastes a business tester's day.
EntryTesters can sign in with the access they need, and the test data existsOtherwise the first day goes on access requests.
EntryEvery requirement has acceptance criteria and at least one scenarioNothing is accepted by default.
ExitEvery scenario was run: none is Not run or BlockedA scenario nobody could run has not been accepted.
ExitEvery scenario passed, or its defect is a written condition of sign-offFailures are either fixed or accepted in the open.
Exit0 open defects of blocker or critical severityThe severity rules below decide what blocks.
ExitEvery open major defect has an accepted workaround, an owner and a fix dateWorkarounds are agreed, not assumed.

Business testers and roles

Pick business testers who do the work every day: the customer service lead who handles payment complaints, the finance analyst who reconciles the export. They notice what a specification misses. Give each tester the scenarios for their own process, and a 30-minute walkthrough of the scenarios and of how to record a result and a defect before UAT starts.

Three other roles make UAT work. The business owner agrees the scope and criteria and makes the decision. The UAT lead, usually from QA, prepares the environment and data, runs a short daily status and triages defects with the testers, so nobody argues severity alone. A developer on call fixes defects and deploys them to the UAT environment, so retests happen inside the window.

The scenario table

Scenarios describe a business task and its outcome in the tester's words, not every click. Business testers follow their real process, which is the point: they find the step the specification forgot. Each scenario gets a result of Passed, Failed, Blocked or Not run, with the date and any defect.

Scenarios can depend on each other. In the example, UAT-4 and UAT-5 use the order placed in UAT-3, so the scenario says so and they run in order.

Example scenarios from the UAT template
IDRequirementScenarioExpected resultTester
UAT-1REQ-12Sign in as a returning customer, add one item and check out with the saved cardCard preselected; order confirmed; email within 5 minutes showing the last four digitsCustomer service team lead
UAT-2REQ-13Check out with the decline test card, then find the attempt in the admin console“Your card was declined” shown; cart unchanged; attempt visible on the customer's recordCustomer service team lead
UAT-3REQ-14Apply SPRING15 to a basket with one full-price and one sale item15% off the full-price item only; the sale item price is unchangedMarketing manager
UAT-4REQ-14The next morning, find the UAT-3 order in the finance exportThe discount is on its own line and matches the orderFinance analyst
UAT-5REQ-17Refund the UAT-3 order in full from the admin consoleOrder shows Refunded; refund equals the amount charged after the discountFinance analyst

Defect severity rules for UAT

Severity decides what blocks sign-off, so agree the rules before UAT starts and apply them the same way to every defect. In UAT, severity is judged by the impact on the business process, not on the code. If a tester and a developer disagree, the UAT lead decides from the table; the business owner can only relax it by accepting a written condition.

The Excel version counts open defects by severity on its Summary sheet, next to the scenario results, and says whether UAT is ready for sign-off.

Defect severity and its effect on UAT sign-off
SeverityMeaning in UATEffect on sign-off
BlockerThe process cannot be completed at all, and there is no workaroundBlocks sign-off. Fix and retest.
CriticalMoney, data or customer trust is wrong, for example a wrong amount charged or refundedBlocks sign-off. Fix and retest.
MajorThe process works only with a workaround, or an acceptance criterion is partly metBlocks, unless the business owner accepts the workaround as a written condition with a fix date
MinorWrong but harmless: confusing text, an extra stepDoes not block. List it in the release notes or backlog.
TrivialCosmetic onlyDoes not block.

The sign-off block

Sign-off is the business owner's decision, recorded with the evidence it was based on. Each signer gives a name, a role, a decision, a date and any conditions. The template offers three decisions: Accepted, Accepted with conditions and Rejected.

A condition is only useful if it can be checked later. It names the defect or criterion, what happens until it is met, who owns it and by when. In the example, the business owner accepts the release with BUG-52 open, on condition that it is fixed by a date and that finance adds discounts by hand from the order report until then. “Accepted, minor issues to follow” is not a condition.

Ask the UAT lead to sign as well, to confirm that the evidence is complete: every scenario has a result and every defect has a severity and a status. The decision and its conditions then go into the test summary report for the release.

The sign-off block of the UAT template, filled in
SignerRoleDecisionDateConditions
Business ownerHead of e-commerceAccepted with conditionsYYYY-MM-DDBUG-52 fixed by an agreed date. Until then the finance analyst adds discounts by hand from the order report.
Co-signerFinance leadAcceptedYYYY-MM-DDNone
Evidence checkUAT leadEvidence completeYYYY-MM-DDNone

Common mistakes

  • Starting UAT before QA is finished. Business testers end up doing system testing and lose faith in the build.
  • Giving business testers QA scripts. Click-by-click scripts test the specification again. Business scenarios test the job.
  • No named decision maker. “The business” cannot sign. A person with a role can.
  • Severity argued per defect. Without rules agreed in advance, every defect becomes a negotiation in the last meeting.
  • Silent conditions. A release accepted “with a few things to fix” and no list, owner or date has been accepted without conditions.
  • No time to retest. Plan the window so failed scenarios can be fixed and run again before the decision.

Running UAT in TestPlum

A spreadsheet works for a handful of scenarios and one business owner. It gets harder when results arrive from several testers at once, when the business owner wants to see the evidence, or when an auditor asks who approved the release and on what basis.

In TestPlum, each requirement keeps its acceptance criteria (one per line) and the tests that verify it, and its status is worked out from the latest results: not covered, not run, failing, partial or passing. The traceability matrix shows requirements down the side, tests across and results in the cells. Business testers record results in a run, with screenshots attached as evidence, and a failed result can be reported as a bug from the same screen. Sign off on a run locks its results, so nobody changes them by accident.

A release has its own runs, requirements and thresholds. Print report gives a page for the decision meeting with sign-off lines, and Ship records the verdict at that moment with the name and time. On the Business plan, a release can require up to five electronic signatures, each with a meaning such as “Approved for release” and each by a different person who confirms with their password or single sign-on. If the release changes afterwards, a signature stays on file but no longer counts. By default, signing is a permission of the Manager project role. See release readiness and the user guide.

People who only need to see tests, results, bugs and reports, such as a sponsor following UAT, can be viewers, which are free on every plan. Business testers who record results and report bugs need a role that can do that, and count as testers. See pricing.

Download

Frequently asked questions

What is a UAT test plan?

A plan for user acceptance testing: the business processes to accept, the acceptance criteria for each requirement, entry and exit criteria, who tests and who decides, the scenarios, the rules for which defects block, and a sign-off block. It ends in a decision, not just a set of results.

What is the difference between UAT and QA testing?

QA testing checks that the software works as specified, usually by testers, across many detailed tests. UAT checks that it does the job the business needs, by the people who will use it, through a few realistic scenarios. UAT normally starts after QA testing has met its exit criteria.

Who should sign off UAT?

A named business owner who is accountable for the process the change affects, such as the head of the team that will use it. Others, such as a finance lead, can co-sign for their area, and the UAT lead can sign to confirm the evidence is complete.

Can UAT be signed off with open defects?

Yes, if the severity rules allow it and the decision says so. In this template, blocker and critical defects always block; a major defect can be accepted as a written condition with a workaround, an owner and a fix date; minor and trivial defects are listed in the release notes or backlog.

Should UAT scenarios be written step by step?

Usually not. Describe the business task and the expected outcome in the tester's own words, and let them follow their normal process. Detailed step-by-step scripts belong in system testing, where the test case template fits better.